Nevsun Provides Bisha Zinc Expansion Project Update

Canada's Nevsun defends Eritrea mining after damning UN report

Eritrean Business News: Vancouver, BC – Nevsun Resources Ltd. (TSX:NSU / NYSE MKT:NSU) announced today that its Bisha Mine zinc expansion project (the “Project”) is on schedule and well under budget.  The Project is on-track for ore commissioning in mid-Q2 2016 and commercial production later in 2016.

HIGHLIGHTS

  • Zero lost time injury incidents to date on the zinc expansion
  • Significantly under budget with estimated cost now $80 million 
  • On schedule for ore commissioning mid Q2 2016 with zinc plant over 90% complete 

The Project enables processing of the primary copper-zinc-gold-silver ore at up to 2.4 million tonnes per year, producing both copper and zinc concentrates from the existing copper flotation and new zinc flotation plants.  Based on the current open pit mine plan, Nevsun expects Bisha to produce on average 225 million pounds of zinc and 53 million pounds of copper in concentrate per year through 2025.  As previously announced, Nevsun will release the 2016 Outlook in the second week of February 2016.

The forecasted total cost will be approximately $80 million, significantly under the budget of $100M.

A Project photo gallery is regularly updated to track visual progress and can be found at: www.nevsun.com/projects/bisha-main/gallery/

Detailed Zinc Expansion Project Progress

The Project is proceeding well on health and safety performance. The Project maintains a zero lost time injury status, with zero environmental non-conformances.

Overall the Project is over 90% complete. All major equipment and materials have been delivered to site and procurement activities are limited to site based orders and amendments. The structural, mechanical, piping and plate work is 98% progressed. The electrical and instrumentation installation is well advanced. The power upgrade from Aggreko has been completed. The search and selection process for the commissioning team for the Project has nearly been completed. Cold commissioning has commenced in certain areas. Primary ore commissioning is planned for mid Q2 2016.

Zinc Concentrate Bulk Handling Update

As the total tonnage of copper and zinc concentrate produced going forward is expected to be similar to total copper concentrate quantities in 2015, there is no need for additional transport or shipping infrastructure upgrades.  The existing Rotainer trucking and loading system continues to operate safely, efficiently and in an environmentally sound manner.

About Nevsun Resources Ltd.

Nevsun Resources Ltd. is the 60% owner of the high grade Bisha Mine in Eritrea.  Bisha has over 9 years of reserve life, generating revenue from both copper and zinc concentrates containing gold and silver by-products.  Nevsun has a strong balance sheet with over $US 400 million in cash, no debt and pays a peer leading quarterly dividend.  Nevsun is well positioned to grow shareholder value through exploration at Bisha and acquisition of additional mining assets.

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close